Cleaning
Cleaning of the Pipelines is of utmost importance during Pipeline pre-commissioning in order to remove mill scales and construction debris. Pipeline cleaning is achieved by Running a series of brush pigs from the Launcher to the Receiver. Pipeline material and Internal coating determines the type of bristles on the brush pigs.
Generally dry Oil free Compressed air is used as pigging medium for cleaning of onshore Pipelines. Cleaning, Gauging and Flooding of subsea pipelines are achieved by propelling a single pig train that consist of Brush, Gauge and Batch Pigs. number of brush pigs in the train will vary based on the length of the pipeline. propelling medium can be treated/untreated filtered fresh water or filtered and chemically treated sea water.
Pipeline cleaning has the following benefits
- Minimises retention of water within the scales post dewatering thus preventing further corrosion
- Reduces flow resistance
- Improves Product quality
- Reduces potential damage to valves and clogging of filters due to debris intrusion
Gauging
Gauge pigs are run to confirm mechanical integrity of a pipeline at various stages of construction. A gauge pig is a bidirectional disc pig fitted with an aluminium or steel plate of 6-10 mm thick that deforms when it comes across an obstruction in the pipeline that is not within tolerance. The diameter of the gauge plate is a predetermined size to considering variance tolerances, this is usually 90-97% of the Pipeline ID
Gauging is performed by a bidirectional pig to in order for it to be reversed in case it becomes stuck. when the gauge plate comes in contact with an obstruction in the pipeline it deforms and gives a visual indication that the pipeline ID is not within the acceptable limits. Gauging indicates that there is an obstruction in the pipeline however it doesn’t indicate the location of the obstruction. Location of the obstruction shall be identified by caliper pigging.
Gauging of onshore Pipelines is usually carried out as a single segment or multiple sections depending on the length of pipeline where as gauging of subsea pipelines is achieved by a combined FCG ( Flood, Clean and Gauge) run
Flooding
The pipeline must be filled with filtered and chemically treated water before the pipeline can be Hydrotested, untreated water may be permitted based on how long the water would remain in the pipeline. flooding achieved by propelling batch pigs from one end of the test section to the other with the hydrotest medium which is usually chemically treated/untreated filtered water.
Hydrotest
Hydrotesting Includes pressurization of pipelines above the design pressure and holding the pressure for the specified period of time. Hydrotest consists of a strength test and a leak test. These tests either combined, or conducted separately based on the construction schedule. air content calculations are performed during pressurization to ensure the air in the flooding water is ≤ 0.2%
The strength test identifies inherent faults in or damages to the pipeline, relieves residual stresses from construction activities, and demonstrates that the pipeline has adequate strength to transport the product safely. The leak test proves that the pipeline is free of leaks. Leak test pressure is usually less than the strength test pressure. Pressure temperature variation calculations are performed at the end of the test to determine any drop in pressure during the test is attributable to leaks or temperature changes,
Dewatering
After the pressure test, the test section need to be bulk dewatered in order to prepare for drying. Dewatering is usually achieved by a train of pigs propelled through the pipeline by air, nitrogen, or product.
Drying
Most of the Hydrocarbon pipelines require drying to a specified dewpoint post Dewatering. Pipeline drying is carried out in order to prevent corrosion, contamination of equipment, enhance export product quality. Drying of pipelines also minimises possibility of hydrate formation during gas in.
Drying of pipelines can be achieved by several methods such as chemical swabbing, Air drying, Nitrogen drying and vacuum drying, air drying, and nitrogen drying. The method of drying will depend on the type of pipeline, dryness requirement, location (onshore/offshore), and length of pipeline
- Chemical Swabbing
Chemical swabbing conditions pipelines designed to carry gas or refined product. Methanol, MEG, TEG are commonly used for this purpose. Chemical swabbing is usually carried out on pipelines where high degree of dryness is not required. Swabbing chemicals are batched between pigs and propelled from one end of the pipeline to the other end with dry air, nitrogen gas or product. Chemical swabbing can be carried out together with dewatering run or separately post dewatering. most of the water is removed from the pipeline during chemical swabbing. any minor quantities of water that remains in the pipeline after chemical swabbing is mixed with sufficient quantities of the swabbing chemical, these chemicals significantly lower the freezing point of water thus preventing formation of hydrates during introduction of gas.
- Air/Nitrogen drying
Air/Nitrogen drying of pipelines is carried out by running several foam pigs from one end of the pipeline to the other with dry compressed air or nitrogen gas post dewatering.
Air compressors and desiccant air dryers used for air drying, the dryers can generally attain a dewpoint of -40° C to -60°C at the outlet, however high ambient temperatures and high humidity levels will have an impact on the efficiency of the drier.
Nitrogen drying is carried out by propelling the foam pigs with nitrogen gas instead of air, nitrogen drying is usually the preferred method for short length pipelines,
- Vacuum Drying
Vacuum drying is based on the principle of creating a vacuum to lower the pressure in the system below the vapor pressure of water causing the water to boil at ambient temperature, high capacity vacuum pumps are used to get desired vacuum levels in the system being dried. these vacuum pumps create vacuum in the pipeline thus causing the water to boil then sucks the vapours out. Vacuum drying is the best method to achieve high degree of dryness, however it is important that the pipeline has been dewatered thoroughly prior to vacuum drying, any pooled water remaining in the pipeline will increase the drying duration significantly.
Inerting
The Pipelines require to be purged with Nitrogen gas prior to introduction of hydrocarbons. Purpose of nitrogen purging is to achieve oxygen levels down to 2-5%. Different combination of equipment are available for Inerting , these include Nitrogen gas quads, liquid nitrogen supplied in tanks, ambient vaporizers, high pressure nitrogen converters, membrane units etc.. type of equipment is chosen based on the length, size, volume and location of the pipeline.
Caliper Survey
During Pre-commissioning Caliper survey is usually carried out after Hydrotest either combined with dewatering or separately post dewatering.
Caliper-Tool is an intelligent inspection system which serves to measure diameter reductions in pipelines – such as dents, ovalities, girth welds, and wall thickness changes – and to detect T-pieces, valves, and other installations. The basic body is the central mechanical element of the Caliper-Tool. All other components are fixed to the basic body.
The cup sleeves fill the cross section of the pipeline and enable the Caliper-Tool to be transported through the pipeline by the medium. The spider measures the inner pipeline diameter at every pipeline position. In addition to the measuring data from the spider, the distance data generated by odometer wheels is continuously acquired and stored together with the individual diameter values.
The internal locator unit transmits electromagnetic signals, which allows the Caliper-Tool to be located by an external inspection tool locator. Caliper tool can be propelled through the Pipeline using compressed air / nitrogen gas / product as pipeline medium.
Pipeline Chemical Cleaning
Gas export pipelines require very high degree of cleanliness to ensure quality of the product being exported. surfactant and or gel cleaning are carried out in addition to mechanical cleaning to achieve the required level of cleanliness.
Surfactant and gel cleaning can be carried out during pre-commissioning and while the pipeline is in operation. Pig trains consisting of brush and batch pigs with slugs of surfactant/gel in between them are propelled from one end of the pipeline to the other to complete cleaning.
Generally hydrocarbon based surfactants are used for pre-commissioning cleaning and cleaning of live pipelines, water based gels are generally used for cleaning during pre-commissioning, and hydrocarbon based gels are used for cleaning of operational pipelines.
Sygma engineers analyse the potential accumulated debris in the pipeline, debris loading capability of the proposed gel , size and length of the pipelines etc..